Test Case
Zugo finished the completion test for Fengshan wind farm in Xuwen sucessfully
Date of publication:2019-05-09EIDT:browse:2176

On July 2, 2017, Zugo Electrical Testin Co., Ltd. successfully finished the completion test for the 35kV cable circuit in Fengshan Wind Farm, which owned by China Power Investment Corporation. Fengshan wind farm, located in Zhanjiang City, Guangdong Province, is 30 km away from Xuwen County and 80 km away from Zhanjiang City. The ground elevation of the wind farm is between 5 m and 100 m. The landform is mainly low hills, and the land type is mainly agricultural land. The total installed capacity of the wind farm is 49.5 MW.  This wind farm installed 24 wind turbine system with single-machine capacity of 2 MW, and one with single-machine capacity of 1.5 MW, and matching box-type substations, as well as a 110 kV substation.


During this completion test, our company has carried out professional testing on three long-distance 26/35kV cable circuits and 25 American box transformers in Fengshan Wind Farm. Three Zugo engineers completed the test successfully under the scorching heat of the sun for three days, which has been highly appraised and recognized by the project contractor and Xuwen Power Supply Supervision Company.